Major Events

1912Hitachi, Ltd.
Minenosawa Mine
Horizontal Shaft Pelton turbine and generator (300HP 250kVA 900min-1) started operation.
1915Mitsubishi Heavy Industries, Ltd.
Japan Nitrogenous Fertilizer Company (now JNC Corporation) Naidaijingawa Power Station Horizontal-shaft Pelton turbine (3,680kW) started operation.
1916Mitsubishi Electric Corporation
Yoshioka Mining generator (400kVA 300min-1) started operation.
1930sHitachi, Ltd.Mitsubishi Electric CorporationMitsubishi Heavy Industries, Ltd.
Started exporting hydropower units to overseas.
1959Hitachi, Ltd.
Shikoku Electric Power Co., Inc. Omorigawa Power Station Francis type pump turbine and generator-motor (12,200kW 14,000kVA 400min-1) started operation.
*First reversible pump turbine and generator-motor
1961Hitachi, Ltd.
Kansai Electric Power Co., Inc. Kurobegawa No.4 Power Station Unit No.3 Pelton turbine and generator (95,000kW 95,000kVA 300/360min-1) started operation.
*The largest output Pelton turbine in Japan
1969Mitsubishi Electric Corporation
Chubu Electric Power Co., Inc. Takane Daiichi Power Station Unit No.3 and No.4 generator-motors (100,000kVA 277min-1) started operation.
*The first generator-motor
1969Mitsubishi Heavy Industries, Ltd.
Chubu Electric Power Co., Inc. Takane Daiichi Power Station Unit No.3 and No.4 Deriaz pump turbines (100,000kVA 277min-1) started operation.
*The first reversible pump turbine
1984Hitachi, Ltd.
Venezuela Guri II Power Station Unit No.13,14,11 Francis type turbines (730,000 kW) started operation.
1984Mitsubishi Electric Corporation
Venezuela Guri II Power Station Unit No.11 generator (805,000 KVA 112.5 min-1) started operation.
*The largest air-cooled capacity machine at that time
1993Mitsubishi Electric Corporation
Hokkaido Electric Power Co., Inc. Takami Power Station Unit No.2 generator-motor (105,000kVA 231min-1±10%) started operation.
*The first 100MW-class adjustable-speed pumped storage system in the world
1993Mitsubishi Heavy Industries, Ltd.
Hokkaido Electric Power Co., Inc. Takami Power Station Unit No.2 Deriaz type pump turbine (103,000kW) started operation.
*The first adjustable-speed pumped storage system in the world (Deriaz type)
1993Hitachi, Ltd.
Kansai Electric Power Co., Inc. Okawachi Power Station Unit No.4 Francis type pump turbine and generator-motor (331,000kW 395,000kVA 330-390min-1) started operation.
*The first 300MW-class adjustable-speed pumped strage system in the world
1999Hitachi, Ltd.
Tokyo Electric Power Co., Inc. Kazunogawa Power Station Unit No.1 Francis type pump turbine and generator-motor (412,000kW 475,000kVA 500min-1) started operation.
*The highest head, large capacity Single-stage pump turbine in the world, and the largest capacity generator-motor in Japan at that time.
2000Mitsubishi Electric Corporation
Tokyo Electric Power Company Kazunogawa Power Station Unit No.2 generator-motor (475,000kVA 500min-1) started operation.
2000Mitsubishi Heavy Industries, Ltd.
Tokyo Electric Power Company Kazunogawa Power Station Unit No.2 Francis type pump turbine (412,000kW) started operation.
2007Hitachi, Ltd.
Kyushu Electric Power Co., Inc. Omarugawa Power Station Unit No.4 Francis type pump turbine, generator-motor (310,000kW 345,000kVA 576-624min-1) started operation.
*Fastest adjustable-speed pumped storage system in the world at the start of operation
2009Mitsubishi Electric Corporation
Kyushu Electric Power Co., Inc. Omarugawa Power Station Unit No.3
adjustable-speed generator-motor (319,000kVA 576-624min-1) started operation.
2009Mitsubishi Heavy Industries, Ltd.
Kyushu Electric Power Co., Inc. Omarugawa Power Station Unit No.3
adjustable-speed Francis type pump turbine (310,000kW) started operation.
2010Mitsubishi Electric Corporation
Slovenia Avče Power Station generator-motor (195,000kVA 600min-1 -4%~+4.3%) started operation.
*The first adjustable-speed pumped storage unit exported to oversea.
2010Mitsubishi Heavy Industries, Ltd.
Slovenia Avče Power Station Francis type pump turbine (185,400kW) started operation.
*The first adjustable-speed pumped storage unit exported to oversea.
2011Establishment of Hitachi Mitsubishi Hydro Corporation(Integration of the hydroelectric power generation system businesses of Hitachi, Ltd., Mitsubishi Electric Corporation, and Mitsubishi Heavy Industries, Ltd.)
2016Hitachi Mitsubishi Hydro Corporation
Tachiachi Hydro Power Station Chingshan Branch Power Station in Republic of China
Francis turbine and generator (96,130kW 115,500kVA 360min-1)
started operation.
2018Hitachi Mitsubishi Hydro Corporation
Kansai Electric Power Co., Inc. Okutataragi Power Station Unit No.2 Francis type pump turbine and generator-motor (311,100kW 350,000kVA 300±15min-1) started operation.
*The first in the world to renovate a pump turbine and a generator-motor from conventional pumped storage power plant to adjustable-speed pumped storage power plant at the same time
2019Hitachi Mitsubishi Hydro Corporation
Laos Nam Ngiep 1 Power Station Main Power Station Francis turbine and generator (140,500kW 162,000kVA 214min-1) started operation.
2019Hitachi Mitsubishi Hydro Corporation
Laos Nam Ngiep 1 Power Station Reverse Regulation Station Bulb turbine and generator (18,790kW 21,500kVA 142.9min-1) started operation.
2019Hitachi Mitsubishi Hydro Corporation
Hokkaido Electric Power Co., Inc. Takami Power Station Unit No.2
Deriaz type pump turbine and generator-motor
(126,000kW 128,500kVA 231±23min-1) started operation.
*Major renovation of adjustable-speed pumped storage power plant
2020Hitachi Mitsubishi Hydro Corporation
Kansai Electric Power Co., Inc. Okawachi Power Station Unit No.4
generator-motor (395,000kVA 330-390min-1) started operation.
*Major renovation of adjustable-speed pumped storage power plant